Napa Renewable Resources Project

6 Documents in Project

Summary

SCH Number
2013092036
Lead Agency
Napa, City of (City of Napa)
Document Title
Napa Renewable Resources Project
Document Type
NOD - Notice of Determination
Received

Document Description
The City of Napa is proposing a number of improvements at its existing Materials Diversion Facility (MDF) which is located in south Napa County at 802 Levitin Way. The MDF receives and processes all residential and commercial source-separated recyclables and yard waste generated within the City and collected by the City's authorized operator Napa Recycling and Waste Services. The MDF also receives and processes materials delivered by haulers servicing surrounding jurisdictions (such as unincorporated Napa County) and by private (self-haul) customers. The proposed Project consists of a Use Permit to be issued by the City of Napa for the operational changes and new technologies at Napa MDF for the "Napa Renewable Resources Project" However, many of the key aspects of the project will not change.

Contact Information
Jeff Freitas
City of Napa
PO Box 660
Napa, CA 94559

707 257 9312

Location

Coordinates
38°12'37"N 122°15'53"W
Cities
Napa
Counties
Napa
Cross Streets
Levitin Way, Tower Road and Devlin Road
Total Acres
18.6
Parcel #
57-110-49, 52, 65, 66, 67, 68
State Highways
Hwy 29 and 12
Railways
SPRR
Airports
Napa County
Waterways
Napa River
Township
5N
Range
4W
Base
MDB&M

Notice of Determination

Approving Agency
City of Napa
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
City of Napa Community Development Department, 1600 First Street, Napa CA 94559

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search