Approve the Campus Master Plan Revision for the Student Housing South Project

4 Documents in Project

Summary

SCH Number
2013091085
Lead Agency
California State Polytechnic University, San Luis Obispo
Document Title
Approve the Campus Master Plan Revision for the Student Housing South Project
Document Type
NOD - Notice of Determination
Received
Posted
5/22/2014
Present Land Use
Parking and Outdoor Recreation/Athletics
Document Description
The proposed revision to the campus master plan revision for the Student Housing South project combines and relocates the four planned student housing facilities to the existing Parking Lots G-1 and R-2 on a 12 acre site at the corner of Slack Street and Grand Avenue in the southeast portion of the campus. Project will provide approximately 1,475 beds in seven residence halls (three- to five- stories) totaling approximately 525,000 gross square feet (GSF). A new parking structure will be situated on the northern end of the site with primary access off Grand Avenue via the existing access road to Parking Lot g-1. The parking structure will be a maximum of four stories, with on to two stories below grade, and surrounded by a visitor's center, cafe, student gathering spaces, housing and residential life staff offices, and a community mail room.

Contact Information

Name
Joel Neel
Agency Name
California State Polytechnic University, San Luis Obispo
Contact Types
Lead/Public Agency

Location

Cities
San Luis Obispo
Counties
San Luis Obispo
Cross Streets
Grand Avenue and Slack Street
Zip
93407
Total Acres
12
State Highways
Hwy 101, 1
Railways
UPRR
Airports
No
Schools
Former Pacheco ES
Waterways
Stenner Creek, Brizzolara Creek
Township
23
Range
12E
Section
30S

Notice of Determination

Approving Agency
Trustees
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.