Relocation of Aufdenkamp Connection Transmission Main (ACTM) (Lake or Streambed Alteration Agreement No. 1600-2019-0140-R5)

10 Documents in Project

Summary

SCH Number
2013091026
Lead Agency
California Department of Transportation, District 12
Document Title
Relocation of Aufdenkamp Connection Transmission Main (ACTM) (Lake or Streambed Alteration Agreement No. 1600-2019-0140-R5)
Document Type
NOD - Notice of Determination
Received
Posted
6/26/2019
Document Description
The California Department of Fish and Wildlife (CDFW) has executed Lake and Streambed Alteration Agreement number 1600-2019-0140-R5, pursuant to section 1602 of the Fish and Game Code to the project Applicant, Santa Margarita Water District. The proposed project involves relocating an underground water main pipeline to accommodate a California Department of Transportation and Orange County Transportation Authority joint freeway widening project. The existing pipe will be excavated, removed through trenching, and a new pipe installed, encased in concrete, and the trench backfilled. The surface treatment of grouted riprap will be returned to its pre-project condition. The project will result in 0.061 acre (120 linear feet) of temporary streambed impacts.

Contact Information

Name
Simona Altman
Agency Name
Department of Fish and Wildlife Region 5
Contact Types
Lead/Public Agency

Location

Counties
Orange
Cross Streets
Interstate 5 bridge at Aliso Creek

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print