Laguna Niguel to San Juan Capistrano Passing Siding project
5 Documents in Project
Summary
SCH Number
2013091008
Lead Agency
Orange County Transportation Authority
Document Title
Laguna Niguel to San Juan Capistrano Passing Siding project
Document Type
NOD - Notice of Determination
Received
Posted
9/25/2018
Present Land Use
commercial, parkland, agriculture, transportation/Agri-bus, community park, open space, planned community, single-family
Document Description
The project consists of the following features: Construction of 1.8 miles of new passing siding railroad track; relocation of an existing spur track; Construction of new retaining walls; Relocation of existing power poles, fiber optic cables, water and sewer lines; Extension of casings for gas, water, and sewer lines; Removal of CP Avery (MP 193.9); Culvert extensions and toher drainage refinements; Addition of a railroad bridge or box culvert at MP 194.6; Asphalt paving adjacent to Camino Capistrano to accomodate paring for use by railroad at MP 194.6; Reprofiling of approximately 600 feet of Camino Capistrano adjacent to Rancho Capistrano in order to improve grades.
Contact Information
Name
Darren Bradford
Agency Name
RWQCB - San Diego Region
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Laguna Niguel, San Juan Capistrano
Counties
Orange
Cross Streets
Camino Capistrano and SR 73
Zip
92675
Total Acres
3.2
State Highways
I-5
Railways
Metrolink Lossan Corridor
Schools
Capistrano Valley HS
Waterways
Oso Creek and Trabuco Creek
Township
7S
Range
8W
Section
25
Base
SBB&M
Notice of Determination
Approving Agency
RWQCB - San Diego Region
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No