Bay Area Products Line Pipeline INtegrity Management Repair Project

Summary

SCH Number
2013088314
Lead Agency
Fish & Wildlife 3 (Napa) (California Department of Fish and Wildlife, Region 3)
Document Title
Bay Area Products Line Pipeline INtegrity Management Repair Project
Document Type
NOE - Notice of Exemption
Received

Document Description
The project proposes to conduct repairs on two sections of the Bay Area Products Line (BAPL) pipeline system, along the Richmond to Avon section of the BAPL. The Chevron Pipeline Company (CPL) proposes to complete on site investigations of the BAPL to assess anomalies in the system. The assessment and repair will require a section of the pipeline to be excavated and trenched at two (2) separate site locations. Equipment to be used includes rubber tire backholes, track excavator, welding truck, water truck, pick-up truck, and hand tools. SAA #1600-2013-0175-R3.

Contact Information
Robert Stanley
California Department of Fish and Wildlife, Region 3
7329 Silverado Trail
Napa, CA 94558

707 944-5573

Location

Cities
Richmond
Counties
Contra Costa

Notice of Exemption

Exempt Status
Statutory Exemption
Type, Section or Code
21080.23
Reasons for Exemption
The project is less than eight miles in length, the length of disturbance is less than one-half mile at any given time, the pipeline is not within eight miles of a pipeline that has been exempted previously in the past 12 months, the project is not solely for the excavation of soil contaminated with hazardous material, plans have been prepared as required by law by the applicant undertaking the project in advance to the appropriate agencies in the event of an emergency evacuation of the public close to the proximity of the project.