Los Gatos Creek Bridge Replacement South Terminal Phase III (Streambed Alteration Agreement No. 1600-2015-0450-R3)

4 Documents in Project

Summary

SCH Number
2013082087
Lead Agency
Peninsula Corridor Joint Powers Board
Document Title
Los Gatos Creek Bridge Replacement South Terminal Phase III (Streambed Alteration Agreement No. 1600-2015-0450-R3)
Document Type
NOD - Notice of Determination
Received
Posted
4/6/2017
Present Land Use
City of San Jose: Mixed Use Commercial; Open Space, Parklands and Habitat; and Combined Industrial/Commercial
Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2015-0450-R3, pursuant to section 1602 of the Fish and Game Code to the project Applicant, Peninsula Corridor Joint Powers Board. Project replaces a two-track railroad bridge with a three-track railroad bridge. The existing bridge is 230 feet long and the new bridge will be 240 feet long. The existing bridge is 30 feet wide and will be 55 feet wide. A cofferdam will be placed upstream and downstream of the construction area. The creek water between the cofferdams will be directed through a 18-24 inch pipe. Geo-grid and rock slope protection will be installed on slopes. Mitigation planting will occur within the rock slope protection. Tree root wads will be installed to deflect stream flows away from the bank and to provide habitat for aquatic and wildlife species.

Contact Information

Name
Kristin Garrison
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
San Jose
Counties
Santa Clara
Cross Streets
W. San Carlos Street and Dupont Street
Zip
95126
Total Acres
4.1
Parcel #
22801002; 22801003; 22805003; ...
State Highways
Hwy 87
Railways
Caltrain and UPRR
Airports
Mineta San Jose Int'l Airport
Schools
Gardner & St. Leo the
Waterways
Los Gatos Creek
Township
7S
Range
1E
Section
17/18

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.