Anderson Dam Seismic Retrofit Project Partially Recirculated Draft Environmental Impact Report

3 Documents in Project

Summary

SCH Number
2013082052
Lead Agency
Santa Clara Valley Water District
Document Title
Anderson Dam Seismic Retrofit Project Partially Recirculated Draft Environmental Impact Report
Document Type
EIR - Draft EIR
Received
Present Land Use
Agriculture, Hillside, Open Space, Recreation, Residential
Document Description
The proposed Project is located at Anderson Reservoir and areas along Coyote Creek in Santa Clara County, California. Anderson Reservoir is Valley Water’s largest water storage facility, but due to restrictions has not been able to operate to full capacity since 2009. The Project involves retrofitting and upgrading Anderson Dam and its associated facilities to meet public safety requirements by the Federal Energy Regulatory Commission (FERC) and California Department of Water Resources Division of Safety of Dams. Specifically, the Project would correct dam safety deficiencies that were identified between 2008 and 2016. The Project would allow Valley Water to maximize water supply and related benefits, while avoiding and minimizing environmental impacts. The Project also includes decommissioning the hydroelectric facility at the dam, implementing Conservation Measures along Coyote Creek to avoid and minimize adverse impacts, and conducting habitat and species monitoring during construction. Upon completion of the dam seismic retrofit, Anderson Reservoir would return to its original storage capacity. For post-construction operations, the Project includes: implementing Fish and Aquatic Habitat Collaborative Effort Phase 1 reservoir releases (flow measures) at the retrofitted Anderson Dam facility, continuing maintenance of the dam once the retrofit has been completed, operations and maintenance of Conservation Measures, and implementing an adaptive management program to monitor and adaptively manage reservoir releases and Conservation Measures to assure that they achieve their objectives. The Draft EIR for the Project was circulated for public review between September 1 and November 8, 2023. After circulation of the Draft EIR, Valley Water met with the Project Board of Consultants (BOC), which reviews the Project and makes recommendations to FERC, to discuss updated design plans and construction sequencing. In response to that meeting and BOC recommendations, Valley Water now proposes to make certain construction changes to the seismic retrofit component, such as extending daily work hours, adding some weekend days, and beginning work on certain Project components sooner. These proposed changes would allow Valley Water to construct planned Project components within the planned construction timeline before the wet season each year to improve its ability to complete the Project on schedule. Valley Water is also introducing a revision to Best Management Practice AQ-1 (Use Dust Control Measures), updating estimates for average and maximum daily workers, adding two noise sensitive receptors, and making minor editorial clarifications. These Project changes necessitated revisions to portions of the aesthetics, air quality, greenhouse gas emissions, and noise and vibration sections of the Draft EIR, which are reflected in the Partially Recirculated Draft EIR. In addition, two appendices to the Draft EIR—Appendix E for air quality and greenhouse gases and Appendix M for noise and vibration—have been revised in the Partially Recirculated Draft EIR to reflect the Project changes, as well as to provide additional technical documentation of the EIR impact analyses. Pursuant to CEQA Guidelines Section 15088.5(f)(2), if the Draft EIR revision is limited to a few chapters or portions of the Draft EIR, the lead agency need only recirculate the chapters or portions that have been modified. The changes to the Project being recirculated would not substantially change the information, analysis, or significance conclusions in the remaining sections of the Draft EIR. Therefore, those sections are not included in the Partially Recirculated Draft EIR. Pursuant to Section 15088.5(f)(2) of the CEQA Guidelines, Valley Water directs that reviewers of this Partially Recirculated Draft EIR limit their comments to those that relate to the sections of the Partially Recirculated Draft EIR that have been revised and recirculated. The Partially Recirculated Draft EIR discloses certain significant Project impacts on aesthetics, air quality, greenhouse gases, and noise and vibration, but does not change the significance conclusions for these impacts as compared to the Draft EIR. There would continue to be significant and unavoidable impacts associated with air quality and noise and vibration as a result of the Project. Significant impacts to aesthetic resources and greenhouse gas emissions discussed in the Partially Recirculated Draft EIR would be mitigated to less than significant levels, similar to the Draft EIR. The Project would not be located on a hazardous waste site listed under Government Code Section 65962.5.

Contact Information

Name
Tiffany Chao
Agency Name
Santa Clara Valley Water District (Valley Water)
Job Title
Senior Water Resources Specialist
Contact Types
Lead/Public Agency / Project Applicant

Location

Cities
Morgan Hill, San Jose
Counties
Santa Clara
Regions
Countywide, San Francisco Bay Area
Cross Streets
Coyote Road and Cochrane Road
Zip
95037
Total Acres
1,973
Parcel #
627-14-026, 627-14-009, 627-14-010, 627-14-020, 728-25-017, 728-25-018, 728-34-010, 728-34-011
State Highways
US 101, SR 85
Railways
Caltrans, Union Pacific Railroad
Airports
None
Schools
Live Oak High School, Sobratos High School, Nordstrom Elementary
Waterways
Anderson Reservoir, Coyote Creek
Township
9s
Range
3E
Section
10
Base
Mt. Diab
Other Information
Other APNs: 728-34-015, 728-34-016, 728-34-017, 728-34-018, 728-34-019, 728-34-020, 728-34-021, 728-35-001,729-37-016, 729-37-017, 729-37-018, 729-37-019, 729-37-021, 729-37-022, 729-37-029, 729-37-030, 729-39-017,729-43-022, 729-43-023, 729-43-026, 729-43-027,729-43-032, 729-44-006, 729-45-017, 729-46-001, 729-46-010, 729-48-001, 729-48-002,729-48-003, 729-48-004, 729-48-005, 729-48-006, 729-52-030, 865-06-008, 865-06-010, 678-02-009, 678-02-029, 678-02-030, 678-02-031, 678-02-032, 678-02-034, 725-03-002, 725-03-003, 725-04-002, 725-04-003, 725-05-002, 725-05-005, 725-05-006, 725-05-011, 725-05-014, 725-05-015, 725-05-016, 725-06-004, 725-06-008, 725-07-004, 725-08-001, 725-08-003, 729-50-001, 729-50-002, 729-50-004, 728-34-019, 728-34-020, 728-34-021, 728-35-001, 728-35-022, 728-35-031, 728-45-046, 729-48-005 Other schools: Morgan Hill Aquatics Center, City of Morgan Hill Recreational Preschool, Voices College Bound Academy of Morgan Hill, Shadow Mountain Baptist School, Britton Middle School, Agape Schools, Central High School, Jackson Academy of Math and Music, Morgan Hill Parent Child Nursery School, Santa Clara County Probation Training, Charter School of Morgan Hill, Los Paseos Elementary School, Martin Murphy Middle School, Ledesma (Rita) Elementary School, Baldwin Elementary School, Stratford School, Bertha Taylor Elementary School, and Santa Teresa Elementary School.

Notice of Completion

State Review Period Start
State Review Period End
State Reviewing Agencies
California Air Resources Board (ARB), California Department of Conservation (DOC), California Department of Fish and Wildlife, Bay Delta Region 3 (CDFW), California Department of Fish and Wildlife, Habitat Conservation Planning (CDFW), California Department of Fish and Wildlife, North Central Region 2 (CDFW), California Department of Forestry and Fire Protection (CAL FIRE), California Department of Parks and Recreation, California Department of Toxic Substances Control (DTSC), California Department of Transportation, District 4 (DOT), California Department of Water Resources (DWR), California Energy Commission, California Governor's Office of Emergency Services (OES), California Highway Patrol (CHP), California Native American Heritage Commission (NAHC), California Natural Resources Agency, California Regional Water Quality Control Board, Central Coast Region 3 (RWQCB), California Regional Water Quality Control Board, San Francisco Bay Region 2 (RWQCB), California State Lands Commission (SLC), Office of Historic Preservation, San Francisco Bay Conservation and Development Commission (BCDC), State Water Resources Control Board, State Water Resources Control Board, Division of Drinking Water, State Water Resources Control Board, Division of Water Quality, State Water Resources Control Board, Division of Water Rights
Development Types
Other (Dam)
Local Actions
Dam Retrofit
Project Issues
Aesthetics, Air Quality, Cumulative Effects, Greenhouse Gas Emissions, Noise
Public Review Period Start
Public Review Period End

Attachments

Draft Environmental Document [Draft IS, NOI_NOA_Public notices, OPR Summary Form, Appx,]
Notice of Completion [NOC] Transmittal form

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV Download All Attachments New Search Print