Clover Valley Reservoir Desilting and Supply Pipeline Project

4 Documents in Project

Summary

SCH Number
2013082044
Lead Agency
Placer County Water Agency
Document Title
Clover Valley Reservoir Desilting and Supply Pipeline Project
Document Type
NOD - Notice of Determination
Received
Posted
10/18/2013
Present Land Use
GP: Rural Residential (1- to 10-acre minimum) Z: F-B-X-DR, 10-acre minimum
Document Description
The proposed project involves improving the operational efficiency of the Clover Valley Reservoir system and reducing future downstream siltation entering into the reservoir and Clover Valley Creek. The proposed project would restore the capacity of Clover Valley Reservoir and eliminate the sources of siltation and sediment that are currently being deposited into the reservoir. The project elements consists of (1) desilting the 2.2 acre Clover Valley Reservoir; (2) installing a permanent water supply pipeline from Antelope Canal to the reservoir; and (3) installing a temporary bypass pipeline to support delivery of water to Clover Valley Creek (and downstream water users) during reservoir desiltation activities.

Contact Information

Name
Heather Trejo
Agency Name
Placer County Water Agency
Contact Types
Lead/Public Agency

Location

Counties
Placer
Cross Streets
English Colony Way
Zip
95663
Total Acres
3.933
Parcel #
031-101-068-000, 031-101-023-000
State Highways
Hwy 193
Railways
UPRR
Waterways
Clover Valley Creek, Caperton Canal, Antelope Canal
Township
12N
Range
7E
Section
21
Base
MDB&M
Other Location Info
Penryn

Notice of Determination

Approving Agency
Placer County Water Agency
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.