Area 2 Storm Drain Cross Connection Removal Project - Phase 2 Roosevelt Park

4 Documents in Project

Summary

SCH Number
2013082006
Lead Agency
Modesto, City of (City of Modesto)
Document Title
Area 2 Storm Drain Cross Connection Removal Project - Phase 2 Roosevelt Park
Document Type
NOD - Notice of Determination
Received
Posted
11/26/2018
Present Land Use
Various

Document Description
The Area 2 Storm Drain Cross Connection Removal Project - Phase 2 Roosevelt Park is the second of four phases of cross connection removal projects in the City of Modesto. Phase 2 Roosevelt Park proposes to remove 6 storm drain to sewer cross-connections and twenty failed rock wells within a 51-acre tributary area. In their place, approx. 680 feet of 24-inch and 2360 feet of 36-inch storm drain piping will be installed to convey storm runoff to an underground storm drainage retention/infiltration system at Roosevelt Park. *SEE NOD FOR FULL DETAILS

Contact Information
David A. Felix
City of Modesto
1010 Tenth Street, 4th Floor
Modesto, CA 95354

Phone : (209) 577-5488

Location

Coordinates
37.662°'"N 121.004°'"W
Cities
Modesto
Counties
Stanislaus
Cross Streets
Various
Other Information
Pearl Street to the North, Bronson Ave to the West, Orangeburg Ave to the South, and Virginia Corridor bike/pedestrian trail to the East.

Notice of Determination

Approving Agency
City of Modesto
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
1010 Tenth Street, Modesto, CA 95354

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes