Public Works - Branch Mill Road Bridge Replacement Project

2 Documents in Project

Summary

SCH Number
2013081047
Lead Agency
San Luis Obispo County
Document Title
Public Works - Branch Mill Road Bridge Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
10/8/2013
Present Land Use
Agriculture
Document Description
San Luis Obispo Co. Public Works Dept. is proposing to replace the existing bridge on Branch Mill Road over Tar Spring Creek to improve public safety by replacing the structurally deficient bridge. The Project would replace the bridge on the existing alignment. The road will be closed to the public for up to 5 months in order to replace the existing bridge, and construct the new roadway approaches. A temporary bridge would be placed downstream of the new bridge to allow for farm equipment and contractor access across the creek. The Project will result in the temporary disturbance of 2.19 acres and the permanent disturbance of approximately 1, 4 acres.

Contact Information

Name
Katie Drexhage
Agency Name
San Luis Obispo County
Contact Types
Lead/Public Agency

Location

Cities
Arroyo Grande
Counties
San Luis Obispo
Cross Streets
Huasna Rd, East Cherry Ave
Zip
93420
Total Acres
2.19
Parcel #
047-161-005
Schools
Lucia Mar USD
Waterways
Tar Spring Creek
Township
32
Range
13

Notice of Determination

Approving Agency
San Luis Obispo County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print