Adelanto Wastewater Treatment Plant 2013 Upgrades

2 Documents in Project

Summary

SCH Number
2013071088
Lead Agency
City of Adelanto
Document Title
Adelanto Wastewater Treatment Plant 2013 Upgrades
Document Type
NOD - Notice of Determination
Received
Posted
10/2/2013
Present Land Use
Airport Development District
Document Description
The Adelanto Public Utility Agency Wastewater Treatment Plant 2013 Upgrades will modify and repurpose existing facilities enabling the facility to operate at the previously approved capacity of 4.0 mgd. Existing Biolac basins will be modified and the existing filters will be repurposed. Four additional filters will be installed when the average wastewater effluent flow approaches 3.3 mgd. Two New clarifiers will be constructed. Piping and pump elements related to the existing clarifiers will be reused to the maximum extent feasible. Recycle and waste sludge pumps for the new clarifiers will be purchased and situated in a new structure. Specific physical improvements include: Installation of screen at headworks; construction of two 70-foot diameter clarifiers and construction of a 1,440 square foot building. The environmental document also assesses potential impacts related to the operation of existing percolation Pond 9.

Contact Information

Name
John Sponsler
Agency Name
Adelanto Public Utilities Agency
Contact Types
Lead/Public Agency

Location

Cities
Adelanto
Counties
San Bernardino
Cross Streets
Jonathan and Auburn
Zip
92301
Total Acres
35.88
Parcel #
0459-06-23-25
State Highways
Hwy 395
Airports
SCLA
Township
6N
Range
5W
Section
21

Notice of Determination

Approving Agency
City of Adelanto
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print