South San Francisco / San Bruno WQCP Capital Improvements Projects

6 Documents in Project

Summary

SCH Number
2013062051
Lead Agency
City of South San Francisco
Document Title
South San Francisco / San Bruno WQCP Capital Improvements Projects
Document Type
NOD - Notice of Determination
Received
Posted
9/18/2013
Present Land Use
Public Quasi-Public, Public Lands
Document Description
The proposed project, which would consist of three components: Wet Weather Improvements Project, Green Energy Project, and Digester Replacement Project. The Wet Weather Improvements Project would include secondary treatment improvements and capacity increase to 40 million gallons per day; headworks and stormwater improvements; and aeration basin rehabilitation. The Green Energy Project would involve installation of solar panels to generate 150 kilowatts of solar photovoltaic energy. Under the Digester Replacement Project, two of the existing three digesters would be demolished and replaced at the same location and the third digester would be rehabilitated.

Contact Information

Name
Sam Bautista
Agency Name
City of South San Francisco
Contact Types
Lead/Public Agency

Location

Cities
South San Francisco
Counties
San Mateo
Cross Streets
South Airport Blvd
Zip
94080
State Highways
Hwy 101
Railways
BART
Airports
San Francisco Int'l
Schools
South San Francisco HS, Ponderosa ES
Waterways
Colma Creek

Notice of Determination

Approving Agency
City of South San Francisco
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print