Burlingame Hills Sewer Maintenance District Sanitary Sewer Capacity Improvements Project

3 Documents in Project

Summary

SCH Number
2013062048
Lead Agency
San Mateo County
Document Title
Burlingame Hills Sewer Maintenance District Sanitary Sewer Capacity Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
1/16/2014
Present Land Use
One-Family Residential District (R-1)/Combining Districts (S-10)
Document Description
The proposed project replacement of existing sewer vitrified clay pipe (VCP) with high density polyethylene (HDPE) and polyvinyl chloride pipes (PVC) in two segments of the Burlingame Hills Sewer Maintenance District's (BHSMD) collection system using open trench and pipe bursting construction methods. The specific segments are located along Adeline Drive (approximately 1,920 linear feet) and lower Canyon Road (approximately 2,927 linear feet). The existing 6" and 8" VCP pipes will be replaced with 10" to 12" HDPE and PVC pipes. After replacement, existing laterals along the pipe alignment will be re-connected to the new pipe. Existing brick manholes will also be replaced with concrete manholes.

Contact Information

Name
Mark Chow
Agency Name
San Mateo County Dept. of Public Works
Contact Types
Lead/Public Agency

Location

Cities
Burlingame
Counties
San Mateo
Cross Streets
Adeline Drive, Canyon Road
Zip
94010
Parcel #
Multiple
State Highways
I-280/SR-82
Railways
Caltrain
Schools
Mercy HS/Hoover ES
Waterways
Easton Creek/Mills Creek
Township
4S
Range
5W
Section
23
Base
MDB&M

Notice of Determination

Approving Agency
San Mateo County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print