Curtis Landing Fish Release Site Improvements Project

7 Documents in Project

Summary

SCH Number
2013062018
Lead Agency
California Department of Water Resources (DWR)
Document Title
Curtis Landing Fish Release Site Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
12/5/2013
Present Land Use
Currently used as a fish release site and levee road, zoning is Agricultural-80 Acres and General Plan Designation is Recreation

Document Description
The project will include demolition of the existing fish release system; removal of wood piles within 100 feet upstream and downstream of the existing system; levee road modification; replacement of existing site entrance gate; installation of a reinforced concrete operation pad; replacement of the fish release system; and modifications to the existing associated lighting, electrical, and power systems.

Contact Information
James Herota
Central Valley Flood Protection
Lead/Public Agency
3310 El Camino Avenue, Room 151
Sacramento, CA 95821

Phone : (916) 574-0651

Location

Coordinates
38°1'59.21"N 121°44'12.74"W
Cities
Rio Vista
Counties
Sacramento
Cross Streets
Near intersection of Sherman Island East Levee Road and Sherman Island Levee Road
Zip
94571
Total Acres
2.54
Parcel #
158-070-048
State Highways
Hwy 160
Waterways
San Joaquin River
Township
2N
Range
2E
Section
10
Base
MDB&M

Notice of Determination

Approving Agency
Central Valley Flood Protection Bd.
Approving Agency Role
Responsible Agency
Approved On
Final Environmental Document Available at
3310 El Camino Avenue, Room 151, Sac., CA 95821

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.