Correia Middle School Sports Complex Project

3 Documents in Project

Summary

SCH Number
2013051030
Lead Agency
San Diego Unified School District
Document Title
Correia Middle School Sports Complex Project
Document Type
NOD - Notice of Determination
Received
Posted
9/30/2015
Present Land Use
Institutional - Middle School / RM-1-1 / Institutional and Public Facilities
Document Description
The proposed project is the construction and operation of a new Sports Complex on the Correia Middle School campus. The complex will include: 1) a natural turf softball field that can also accommodate field sports in the outfield area; 2) an artificial turf play field with multiple markings for either one football field or a combination of two other field sports; and, 3) a hard court play area. Additional project features will include: a long jump pit; a classroom/team room building; a restroom / concession / storage building; sports field lighting of the natural and artificial turf play areas; a new paved pedestrian walkway connecting the different sports venues; a new electrical service; new field irrigation and cooling infrastructure; and, landscaping.

Contact Information

Name
Gary Stanford
Agency Name
San Diego Unified School District
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Cross Streets
4302 Valeta Street
Zip
92107
Total Acres
19
Parcel #
449-110-03
State Highways
I-8, 5
Railways
San Diego MTS
Airports
San Diego International
Schools
Multiple
Waterways
Famosa Slough; Pacific Ocean; Mission Bay
Township
16S
Range
3W
Base
SBB&M

Notice of Determination

Approving Agency
San Diego Unified School District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.