Document Description
The proposed project involves improving the Chabot Dam embankment and foundation through cement deep soil mixing (CDSM). The outlet works would be improved by strengthening the outlet pipe and an existing vertical shaft located behind the tower, installing new valves and controls in the vertical shaft, and removing the outlet tower and pavilion. Excavated materials would be stockpiled at the Filter Pond Stockpile and/or Park Stockpile, which are located at the former water treatment filter ponds and Chabot Park, respectively. Two potential haul routes are proposed within the project site: Upper Haul Route and the Lower Haul Route. Following the Chabot Dam seismic upgrade activities, the footprint of the project area would be returned to existing conditions. The entire project site, including haul routes and stockpile areas, is located within EBMUD property.

Contact Information

Name
Bill Maggiore
Agency Name
East Bay Municipal Utility District
Contact Types
Lead/Public Agency

Location

Cities
Oakland, San Leandro
Counties
Alameda
Cross Streets
Estudillo Avenue, San Leandro
Zip
94605
Total Acres
96
Parcel #
Various
State Highways
I-580
Railways
No
Airports
No
Schools
Several
Waterways
San Leandro Creek
Township
2S
Range
2W
Other Location Info
Castro Valley

Notice of Determination

Approving Agency
EBMUD Board of Directors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.