The CA DFW is executing Lake or Streambed Alteration Agreement number 1600-2013-0082-R2, pursuant to Section 1602 of the Fish and Game Code to the project appli

6 Documents in Project

Summary

SCH Number
2013042039
Lead Agency
City of Grass Valley
Document Title
The CA DFW is executing Lake or Streambed Alteration Agreement number 1600-2013-0082-R2, pursuant to Section 1602 of the Fish and Game Code to the project appli
Document Type
NOD - Notice of Determination
Received
Posted
6/24/2013
Present Land Use
Vacant/Office Professional/Office Professional
Document Description
The project is limited to the relocation of an ephemeral drainage to accommodate the construction of a new medical building and parking lot. Approximately 20-feet south of the existing detention basin the drainage will be re-routed ~30 feet east to parallel with Old Tunnel Road. The re-routed drainage will be constructed as an open swell using standard construction equipment. Two additional detention basins will be constructed and lined with cobble for sediment filtration. The western most detention basin will drain by an underground 18-inch diameter culvert into the existing storm drainage system.

Contact Information

Name
Tanya Sheya
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Grass Valley
Counties
Nevada
Cross Streets
Old Tunnel Road - Off Brunswick Road
Zip
95945
Total Acres
5.33
Parcel #
35-400-78
State Highways
Hwy 20/49
Airports
Nevada County
Schools
Sierra College, Nev. Union
Waterways
Wolf Creek
Township
16N
Range
8E
Section
24
Base
MDB&M

Notice of Determination

Approving Agency
DFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes