Santa Barbara County Reliability Project

8 Documents in Project

Summary

SCH Number
2013041070
Lead Agency
Public Utilities Commission (California Public Utilities Commission)
Document Title
Santa Barbara County Reliability Project
Document Type
NOP - Notice of Preperation
Received

Document Description
Major components of the SBCRP include the following: - Reconstruction of existing 66 kilovolt subtransmission facilities primarily within existing utility rights-of-way (ROW) between the existing Santa Clara Substation in Ventura County and the existing Carpinteria Substation in Santa Barbara County (Segments 4 and 3B); - Installation of marker balls on overhead wire; - Modification of subtransmission and substation equipment within the existing Carpinteria Substation, Casitas Substation, and Santa Clara Substation; - Replacement of line protection relays within existing substation equipment rooms or cabinets at Getty Substation, Goleta Substation, Ortega Substation, and Santa Barbara Substation; - Installation of telecommunications facilities along Segments 1, 2, and 4 and at Carpinteria Substation, Casitas Substation, Santa Clara Substation, and Ventura Substation; - Installation of fault return conductor on subtransmission structures along Segment 3A; - Removal of subtransmission infrastructure foundation in Segments 1 and 2;

Contact Information
Lon Payne
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102-3298

415 703 3175

Location

Coordinates
34°24'33.86"N 119°30'54.26"W
Cities
Ventura Santa Barbara Carpinteria
Counties
Ventura Santa Barbara
Cross Streets
Santa Clara Substation, Foothill Rd. northwest to Carpinteria Substation (approx. 36 miles)
Zip
Various
Total Acres
215
Parcel #
Multiple
State Highways
SR 33, 118, 126, 150, 192
Railways
No
Airports
No
Schools
Carpinteria HS, Canaline
Waterways
Franklin Creek, Casitas Creek, Canada Larga
Other Location Info
Buenaventura

Notice of Completion

Review Period Start
Review Period End
Development Type
Power:Electric Transmission Lines (66 kv Watts)
Local Action
Other Action Local Coastal Permit Other Action: PTC (CPUC)
Project Issues
Cumulative Effects Landuse Growth Inducing Wetland/Riparian Water Supply Water Quality Vegetation Traffic/Circulation Toxic/Hazardous Solid Waste Soil Erosion/Compaction/Grading Septic System Schools/Universities Recreation/Parks Public Services Population/Housing Balance Noise Minerals Geologic/Seismic Forest Land/Fire Hazard Flood Plain/Flooding Drainage/Absorption Coastal Zone Biological Resources Archaeologic-Historic Air Quality Agricultural Land Aesthetic/Visual
Reviewing Agencies
California Coastal Commission California Department of Parks and Recreation California Energy Commission California Highway Patrol Caltrans, District 5 Caltrans, District 7 Department of Conservation Department of Fish and Wildlife, Region 5 Department of Water Resources Native American Heritage Commission Regional Water Quality Control Board, Region 3 Regional Water Quality Control Board, Region 4 Resources Agency State Lands Commission