Humboldt Bay Trail Project North (Lake or Streambed Alteration Agreement No. 1600-2016-0086-R1)
5 Documents in Project
Summary
SCH Number
2013032008
Lead Agency
City of Arcata
Document Title
Humboldt Bay Trail Project North (Lake or Streambed Alteration Agreement No. 1600-2016-0086-R1)
Document Type
NOD - Notice of Determination
Received
Posted
6/27/2016
Present Land Use
Multiple City zones - City & NCRA ROW, Natural Resource, Public Facility; Industrial Limited Resid. Low Density, Co. NR, MG
Document Description
Project is limited to one encroachment that includes elements for Phase II of the Humboldt Bay Trail North project. The trail will have a width of 14 feet (10 feet paved with 2 foot shoulders) and will be approx. 3 miles in length, a total of 5 bridges will be constructed along the route including 5 water crossings (table 1). Bridge construction work within the wetted channel will be limited to periods of negative low tides between July 1 and September 31 when water is not present. There will be 1.78 acres of permanent wetland impacts, which have a 4:1 mitigation ratio. Mitigation of wetland impacts will be conducted in accordance with the Humboldt Bay Area Mitigation and the Memorandum of Understanding in place between Caltrans and the City of Arcata.
Contact Information
Name
David Manthorne
Agency Name
CDFW
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Arcata
Counties
Humboldt
Cross Streets
Trail from Sunset Ave through Arcata and west of Hwy 101 to Bracut intersection
Zip
95521
Total Acres
4.5
Parcel #
multiple
State Highways
Hwy 101, 255
Railways
NCRA
Airports
No
Schools
Arcata HS
Waterways
Jolly Giant & Jacoby Creek, Gannon & Butcher Slough
Township
6N
Section
32
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No