Maintenance Dredging of the Federal Navigation Channels in San Francisco Bay Fiscal Years 2015-...

4 Documents in Project

Summary

SCH Number
2013022056
Lead Agency
Regional Water Quality Control Board, Region 2 (San Francisco Bay), Oakland
Document Title
Maintenance Dredging of the Federal Navigation Channels in San Francisco Bay Fiscal Years 2015-...
Document Type
NOD - Notice of Determination
Received
Posted
6/1/2015

Document Description
The Regional Water Board has issued a Clean Water Act Section 401 water quality certification/Waste Discharge Requirements (Order) for USACE's continued maintenance dredging operations in San Francisco Bay for the period of 2015-2019. To avoid in-Bay fish entrainment, the Order requires a reduction in the use of hydraulic hopper dredging equipment in 2017. A statement of overriding consideration was adopted for the two-year period when fish species may be impacted. After this period, the project impacts are less-than significant. Mitigation measures to avoid, minimize and mitigated fish entrainment are required during the initial two-year phase-out period.

Contact Information
Elizabeth Christian
Regional Water Quality Control Board, Region 2 (San Francisco Ba
1515 Clay Street, Suite 1400
Oakland, CA 94612

Phone : (510) 622-2335

Location

Counties
Marin San Mateo Solano
Waterways
San Francisco Bay, Napa and Petaluma Rivers

Notice of Determination

Approving Agency
CA Regional Water Quality Control Board
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
http://www.waterboards.ca.gov/sanfranciscobay/water_issues/programs/dredging/Fed_Nav_Channels_FEAEIR_April... CA Regional Water Quality Control Board, 1515 Clay Street, Suite 1400, Oakland, CA 94612

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes