Jo Smith Nature Trail Pedestrian Bridge (Arcade Creek)

4 Documents in Project

Summary

SCH Number
2013022030
Lead Agency
Arcade Creek Recreation and Park District (ACPRD)
Document Title
Jo Smith Nature Trail Pedestrian Bridge (Arcade Creek)
Document Type
NOD - Notice of Determination
Received
Posted
3/22/2013
Present Land Use
Open space / O / Recreation
Document Description
The project consists of the construction of a new pedestrian creek crossing along the Jo Smith Nature Trail in the Carmichael community. The bridge will be placed just upstream of the current Sacramento Area Sewer District's sewer pipe crossing. The new bridge will be a pre-fabricated metal structure ten feet wide and approximately 200 feet long. The decking on the bridge will consist of a slip resident material to ensure proper footing. New bridge abutments will be constructed on both sides of the creek, and depending on the recommendations from the manufacture, a single support pier may be placed mid-way outside of the wetted stream channel. The new bridge crossing will meet current pedestrian standards and will accommodate future Class 1 bicycle facilities.

Contact Information

Name
Steven Fraher
Agency Name
Arcade Creek Recreation and Park District
Contact Types
Lead/Public Agency

Location

Counties
Sacramento
Cross Streets
Myrtle Ave/Hemlock St
Zip
95841
Total Acres
.5
Parcel #
230-0230-005
State Highways
I-80
Schools
Americal River College
Waterways
Arcade Creek
Township
9N
Range
6E
Base
MDB&M
Other Location Info
City/Nearest Community: Carmichael

Notice of Determination

Approving Agency
Arcarde Creek Recreation and Park District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print