Cressey-Gallo 115 kV Power Line Project
Document Type
NOD - Notice of Determination
Received
Posted
1/21/2014
Present Land Use
Majority designated agriculture and Zoned as General Agriculture; some Agriculture Residential, Single-Family Residential; etc.
Document Description
PG&E is proposing to construct the Cressey-Gallo 115 kV Power Line Project to improve transmission system reliability for customers in north-central Merced County, CA. The project consists of constructing a new 14.4-mile 115 kV power line between Cressey and Gallo Substations to form a power line loop with two other area substations (Livingston and Atwater) to avoid customer service interruptions from single-line outages in this area. The project includes constructing a new, 14.4-mile, single-circuit 115 kV power line interconnecting Cressey Substation and Gallo Substation; upgrading the bus configurations at Cressey Substation and replacing the existing radial power line transition into the substation within the existing substation property; and expanding Gallo Substation to add switchgear and upgrade the bus configurations.

Contact Information

Name
Billie Boulevard
Agency Name
California Public Utilities Commission
Contact Types
Lead/Public Agency

Location

Cities
Livingston
Counties
Merced
Cross Streets
SR 99, West Lane, Meadow Drive, and River Road
Zip
95334
Total Acres
14.4
State Highways
Hwy 99
Railways
BNSF and UPRR
Schools
Schelby School
Waterways
Merced Irrigation District irrigation canals

Notice of Determination

Approving Agency
CA PUC
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.