2012 District Facilities Master Plan

5 Documents in Project

Summary

SCH Number
2013012021
Lead Agency
Ohlone Community College District
Document Title
2012 District Facilities Master Plan
Document Type
NOD - Notice of Determination
Received
Posted
2/14/2014
Present Land Use
Public Facility
Document Description
The 2012 DFMP involves reorganization of facilities and reconfiguration of access and circulation at the Fremont Campus. Activities outlines in the 2012 DFMP include the demolition/removal of some of the existing buildings on the campus, the renovation of some of the existing buildings, and the construction of new buildings. In addition, the 2012 DFMP includes recommended vehicles and pedestrian circulation plans for the campus and recommended landscape improvements. Overall, existing buildings on the campus total approximately 286,746 assignable square feet. After implementation of the 2012 DFMP, the total building space on the campus would be reduced by approximately 2,571 assignable square feet to 284,175 square feet as the Fremont Campus currently has more space than it needs to house the 2023 program of instruction and related supported services.

Contact Information

Name
Ron Little
Agency Name
Ohlone Community College District
Contact Types
Lead/Public Agency

Location

Cities
Fremont
Counties
Alameda
Cross Streets
Mission Boulevard and Witherly Lane
Zip
94539
State Highways
Hwy 238, 680
Schools
Mission San Jose ES

Notice of Determination

Approving Agency
Ohlone College Community District Board of Trustees
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print