Dwight Road Extension and New Warehouse

4 Documents in Project

Summary

SCH Number
2013012017
Lead Agency
Sacramento Regional Sanitation District
Document Title
Dwight Road Extension and New Warehouse
Document Type
NOD - Notice of Determination
Received
Posted
5/7/2013
Present Land Use
Public Quasi-Public/AG-80/Public Quasi-Public
Document Description
The project will construct a new service road and warehouse structure at the Sacramento Regional Wastewater Treatment Plant (SRWTP). The Permittee proposes to extend Dwight Road for approximately 1.25 miles. It would begin at the current northern terminus of Dwight Road, 0.4 miles north of Laguna Boulevard and immediately south of the City of Elk Grove's Laguna West Drainage Chanel. The service road would cross the channel with a single span, concrete bridge that would be supported by seat type abutments. The Dwight Road extension would cross another drainage ditch, in which a culvert would be placed. The service road would then proceed north to the terminus at Glacier Way, the boundary of the operation area of the SRWTP. The proposed Project would cross the Laguna West Drainage Channel with a 65 foot long by 70 foot wide single-span concrete bridge.

Contact Information

Name
Amy Kennedy
Agency Name
Department of Fish and Wildlife
Contact Types
Lead/Public Agency

Location

Cities
Elk Grove
Counties
Sacramento
Cross Streets
Sims Road/Laguna Station Road
Zip
95758
Total Acres
12
Parcel #
Various
State Highways
I-5
Railways
UPRR
Schools
Elk Grove USD
Waterways
Morrison Creek
Township
7N
Range
5E
Section
30
Base
MDB&M

Notice of Determination

Approving Agency
Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.