Faculty Club Renovation and Guest House Addition Project

3 Documents in Project

Summary

SCH Number
2013011036
Lead Agency
University of California, Santa Barbara
Document Title
Faculty Club Renovation and Guest House Addition Project
Document Type
NOD - Notice of Determination
Received

Document Description
The Santa Barbara campus proposes to expand and renovate facilities provided by the Faculty Club. The major project element is the development of 30 guest rooms that would provide additional overnight accommodations for visitors to UCSB. The project includes improvements to existing Faculty Club facilities, including: remodeling interior facilities; renovating exterior areas; utility infrastructure and energy efficiency upgrades; and building code compliance upgrades, including seismic strengthening. The project includes exterior renovations the maximum dining capacity of the Faculty Club would increase from 150 to 282 people. After completion of the project, the sf of the building would be increased from 13,915 to 29,600 gsf. The building would be approximately 40-feet high.

Contact Information
Shari Hammond
University of California
Physical & Environmental Planning 1111 Franklin Street, 6th Floor
Oakland, CA 94607

805 893 3796

Location

Cities
Goleta
Counties
Santa Barbara
Cross Streets
UCSB Main Campus
Total Acres
120,000 sf
Parcel #
073-130-001
State Highways
Hwy 101
Airports
Santa Barbara
Waterways
Campus Lagoon, Pacific Ocean
Township
4N
Range
28W

Notice of Determination

Approving Agency
University of California
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
Campus Planning & Design, University of California, Santa Barbara, CA 93106

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search