South Orange County Reliability Enhancement (SOCRE) Project

6 Documents in Project

Summary

SCH Number
2013011011
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
South Orange County Reliability Enhancement (SOCRE) Project
Document Type
NOD - Notice of Determination
Received
Posted
1/12/2017
Present Land Use
Multiple: Multi-Family/Single Family Residential, Open Space, Recreation/Parks, Industrial, Landfill, Commercial
Document Description
The SOCRE project would include: 1. Rebuilding and upgrading the existing 138/12-kV air-insulated Capistrano Substation (2 acres) as a 230/138/12-kV gas-insulated substation (6.4 acres); 2. Replacing a segment of a single-circuit 138-kV transmission line between the Talega and Capistrano substations with a new double-circuit 230-kV transmission line (7.5 miles), and relocating several transmission and distribution line segments (2 miles, combined) located near the two substations; and 3. Relocating a 12-kV line from the San Juan Capistrano Substation to Prima Deschecha Landfill.

Contact Information

Name
Andrew Barnsdale
Agency Name
California Public Utilities Commission
Contact Types
Lead/Public Agency

Location

Cities
San Clemente, San Juan Capistrano
Counties
Orange, San Diego
Cross Streets
Camino Capistrano, Cristianitos Rd
Zip
Various
Total Acres
16 (permanent)
Parcel #
Multiple
State Highways
I-5, SR-74, 1, 73
Railways
Union Pacific
Airports
No
Schools
San Juan Hills HS
Waterways
Pacific Ocean
Township
8S
Range
8W
Section
1
Base
SBB&M

Notice of Determination

Approving Agency
CA Public Utilities Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes