Hazel Avenue Electrical Facilities Relocation and Expansion Project
4 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2012122037
- Lead Agency
- Sacramento Municipal Utility District
- Document Title
- Hazel Avenue Electrical Facilities Relocation and Expansion Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 3/14/2014
- Present Land Use
- The proposed substatio is currently vacant and zoned low density residential as per the Sacramento County General Plan
- Document Description
- The proposed project consists of dismantling an existing SMUD substation, constructing a new replacement substation, and altering the proposed alignment for the overhead 69,000-volt (69kV) subtransmission line that would connect to the relocated substation. The proposed project would accommodate the County of Sacramento's Hazel Avenue Widening Project and to respond to future demand for electrical service in the service area. In this IS/MND, SMUD evaluated two option substation locations; SMUD's Board of Directors approved Site B (the northern site) for construction of the new replacement substation.
- Contact Information
-
Kim Crawford
Sacramento Municipal Utility District
Lead/Public Agency
P.O. Box 15830 MS B203
Sacramento, CA 95852-1830
Phone : (916) 732-5063
Location
- Coordinates
- 38°39'3.79"N 121°13'31.93"W
- Counties
- Sacramento
- Cross Streets
- Hazel Avenue/Kruitof Way and Hazel Avenue/Timm Avenue
- Zip
- 95628
- Total Acres
- <1
- Parcel #
- 246-0093-021, -022, -005
- State Highways
- Hwy 50
- Waterways
- American River
- Other Location Info
- Hazel Avenue
Notice of Determination
- Approving Agency
- Sacramento Municipal Utility District
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- Sacramento Municipal Utility District, 6201 S Street, CA 95817-1899.
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.