Geary Road Improvements Project--Phase 3

3 Documents in Project

Summary

SCH Number
2012122029
Lead Agency
City of Walnut Creek
Document Title
Geary Road Improvements Project--Phase 3
Document Type
NOD - Notice of Determination
Received
Posted
10/22/2013
Present Land Use
Single- & multi-family uses and semi-public/institutional/mixed-use/comm'l for adjacent Walnut Creek/Pleasant Hill areas
Document Description
The Geary Road Improvements Project--Phase 3 is intended to improve vehicular, bicycle, and pedestrian circulation and safety. The project would include a continuous, dual left-turn center lane; an exclusive, continuous bike lane and continuous pedestrian sidewalk on both sides of the roadway; and landscaping along the entire length of the project area. Traffic signals at Pleasant Hill Road and Buena Vista Avenue would be modified, and street lighting would be upgraded. Drainage improvements would include replacement of a 72-inch-diameter corrugated metal drainage pipe under Geary Road with an underground concrete pipe, replacement of drainage ditches with an underground concrete drainage pipe, and construction of a series of bioretention planting areas and bioretention swales.

Contact Information

Name
Scott Wikstorm
Agency Name
City of Walnut Creek
Contact Types
Lead/Public Agency

Location

Cities
Pleasant Hill, Walnut Creek
Counties
Contra Costa
Cross Streets
Geary Road between Putnam Blvd/Buena Vista Ave & Pleasant Hill Rd/Camino Verde
Zip
94596
Total Acres
4000
State Highways
SR-24, 242, I-680
Waterways
unnamed creek on adjacent parcel

Notice of Determination

Approving Agency
City of Walnut Creek
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print