Brookhurst Street Improvements Project from I-5 to SR 91

5 Documents in Project

Summary

SCH Number
2012121017
Lead Agency
City of Anaheim
Document Title
Brookhurst Street Improvements Project from I-5 to SR 91
Document Type
NOD - Notice of Determination
Received
Posted
3/11/2013
Present Land Use
Developed roadway/ Major Arterial
Document Description
The proposed Brookhurst Street Improvements Project from Interstate 5 to State Route 91 would involve widening an approximate 0.4-mile portion of Brookhurst Street between State Route 91 and Interstate 5. The primary purpose of the Project is to relieve congestion along the roadway and provide continuity in the number of lanes on Brookhurst Street within the City of Anaheim. A secondary purpose is to enhance aesthetics and improve drainage along the corridor. In order to accommodate the additional lanes in the northbound and southbound directions as well as the proposed bikeways, sidewalks, and landscaped areas, the Project proposes to shift the roadway centerline a maximum of 22 feet to the east and widen the roadway right-of-way. The Project would require 19 full and 13 partial property acquisitions along the eastern and western sides of the street.

Contact Information

Name
Tiberius Rosu
Agency Name
City of Anaheim
Contact Types
Lead/Public Agency

Location

Cities
Anaheim
Counties
Orange
Cross Streets
Brookhurst Street and La Palma Avenue
Zip
92801
Total Acres
1.9
Parcel #
multiple
State Highways
I-5, SR 91
Railways
BNSF
Schools
John Marshall, Servite, Orangethorpe
Waterways
Fullerton Channel

Notice of Determination

Approving Agency
City of Anaheim
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print