Shinn Pond Gravity Rediversion Pipeline No. 2

4 Documents in Project

Summary

SCH Number
2012112028
Lead Agency
Alameda County Water District (ACWD)
Document Title
Shinn Pond Gravity Rediversion Pipeline No. 2
Document Type
NOD - Notice of Determination
Received
Posted
4/16/2013
Present Land Use
Public Facilities
Document Description
ACWD proposes to construct a new 54-inch-diameter Gravity Rediversion Pipeline No. 2 with an intake structure in Shinn Pond, a flow meter and isolation valve vault, and an outlet structure into Stevenson Pond. The existing Shinn Pond Pump Station, Stevenson Pond 18-inch-diameter Diversion Pipeline, and Rock Pond Pipeline would be decommissioned and abandoned in place. The project is located in City of Fremont and it is adjacent to Rancho Arroyo Park. The construction is planned to begin in spring of 2013. The CA DFW is executing a Lake and Streambed Alteration Agreement Number 1600-2012-0420-3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Robert Shaver/Alameda County Water District.

Contact Information

Name
Dorota Budzynska
Agency Name
DWR, Div. of Safety of Dams
Contact Types
Lead/Public Agency

Location

Cities
Fremont
Counties
Alameda
Cross Streets
Montecito Dr. (nearest)
Zip
94536
State Highways
SR 238
Railways
UPRR and BART
Schools
Niles ES
Waterways
Alameda Creek & Quarry Lakes
Township
4S
Range
1W
Section
20

Notice of Determination

Approving Agency
DWR
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print