Long-term Contract for the Exchange of Water Between Bureau of Reclamation and BBID and Wholesale Water
2 Documents in Project
Summary
SCH Number
2012102008
Lead Agency
Byron Bethany Irrigation District
(BBID)
Document Title
Long-term Contract for the Exchange of Water Between Bureau of Reclamation and BBID and Wholesale Water
Document Type
NOD - Notice of Determination
Received
Posted
11/28/2012
Present Land Use
Agricultural
Document Description
The Project includes the construction and operation of facilities to allow for the delivery of water supplies to accommodate the anticipated demand of Tracy Hills. BBID would introduce up the 4,500 acre-feet per year of its non-CVP water at the Delta-Mendota Canal between March and October. Introduced water would be exchanged with Reclamation at point of introduction. The CVP water would be treated at the City of Tracy's treatment plant for delivery by the City of Tracy to Tracy Hills.
Contact Information
Name
Rick Gilmore
Agency Name
Byron Bethany Irrigation District
Contact Types
Lead/Public Agency
Address
Phone
Location
Coordinates
Counties
Alameda, San Joaquin
Cross Streets
Kelso Road and Bruns Road
Zip
94514
Total Acres
5.9
Parcel #
099B-7050-001-05
Waterways
BBID Canal 70, USBR Delta Mendota Canal
Township
2S
Range
3E
Section
1
Base
MDB&M
Other Location Info
Byron
Notice of Determination
Approving Agency
Byron Bethany Irrigation District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.