City of Big Bear Lake Department of Water and Power Angel's Camp and Santa Barbara Reservoirs Project

3 Documents in Project

Summary

SCH Number
2012101085
Lead Agency
City of Big Bear Lake
Document Title
City of Big Bear Lake Department of Water and Power Angel's Camp and Santa Barbara Reservoirs Project
Document Type
NOD - Notice of Determination
Received
Posted
10/14/2014
Document Description
The State Water Resources Control Board (SWRCB), as the responsible agency, will be issuing a water supply permit. The City of Big Bear Lake Department of Water and Power (DWP) proposed project includes construction and installation of new water storage and conveyance facilities consisting of two new reservoirs, a booster pumping station, and water distribution system pipelines. The DWP intends to construct these facilities in the Moonridge and Sugarloaf areas. The proposed project is the construction and installation of water reservoirs, a booster pumping station, water distribution pipelines, and associated appurtenances. The proposed water facilities will be located within the DWP's service area within the jurisdiction of the City of Big Bear Lake and the County of San Bernardino. The objective of the proposed water reservoirs, booster pumping station, and distribution pipelines is to enhance fire flow capacity, augment circulation in the distribution system, and reduce energy consumption.

Contact Information

Name
Sean McCarthy
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Location

Cities
Big Bear Lake
Counties
San Bernardino
Cross Streets
Santa Barbara Avenue and Magnolia Lane
Zip
92315
Total Acres
3.4
State Highways
Hwy 38
Township
2N
Range
1E
Section
23-26
Base
SBB&M

Notice of Determination

Approving Agency
SWRCB
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No