Angel's Camp Reservoir and Santa Barbara Reservoir Projects

3 Documents in Project

Summary

SCH Number
2012101085
Lead Agency
City of Big Bear Lake
Document Title
Angel's Camp Reservoir and Santa Barbara Reservoir Projects
Document Type
NOD - Notice of Determination
Received
Posted
12/26/2012
Document Description
The project consists of the construction and installation of new water storage and conveyance facilities consisting of two new reservoirs, a booster pumping station, and water distribution system pipelines. The Department intends to construct these facilities in the Moonridge and Sugarloaf areas. The proposed project is the construction and installation of water reservoirs, a booster pumping station, water distribution pipelines, and associated appurtenances. The proposed water facilities will be located within the DWP's Service Area within the jurisdiction of the City of Big Bear Lake and the County of San Bernardino. The objective of the proposed water reservoirs, booster pumping station, and distribution pipelines is to enhance fire flow capacity, augment circulation in the distribution system, and reduce energy consumption. The Department's Water Master Plan (2006) evaluated existing reservoirs and distribution pipelines within the Department's water service system. Distribution and storage facilities within various areas of the Department's service system were determined to be undersized and deficient to meet fire flow requirements. The proposed new and replacement distribution pipelines would be 12 inches and 8 inches in diameter to meet the Department's fire flow requirements.

Contact Information

Name
Bill La Haye
Agency Name
City of Big Bear Lake
Contact Types
Lead/Public Agency

Location

Cities
Big Bear Lake
Counties
San Bernardino
Cross Streets
Santa Barbara Avenue and Magnolia Lane
Zip
92315
Total Acres
3.4
State Highways
Hwy 38
Township
2N
Range
1E
Section
23-26
Base
SBB&M

Notice of Determination

Approving Agency
City of Big Bear Lake DWP
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print