Interstate 10 Corridor Project

8 Documents in Project

Summary

SCH Number
2012101082
Lead Agency
California Department of Transportation, District 8
Document Title
Interstate 10 Corridor Project
Document Type
NOD - Notice of Determination
Received
Posted
5/22/2017
Present Land Use
Residential, commercial, industrial, resource/utility, undeveloped/vacant, and government
Document Description
The I-10 CP proposes to improve I-10 by constructing freeway lane(s) and other improvements through all or a portion of the 33-mile long segment of the I-10 from the LA/San Bernardino County line to Ford Street in San Bernardino County. The I-10 Corridor Project (I-10 CP) consists of a No Build Alternative (Alternative 1) and two build alternatives (Alternatives 2 and 3). Alternative 3 was selected as the Preferred Alternative.

Contact Information

Name
Aaron Burton
Agency Name
California Department of Transportation, District 8
Contact Types
Lead/Public Agency

Location

Cities
Claremont, Montclair, Ontario, Pomona, San Bernardino, San Bernardino, Claremont, Pomona, Montclair, Ontario, ...
Counties
San Bernardino
Cross Streets
Various from White Ave, City of Pomona to Live Oak Canyon Rd, Yucaipa
Zip
numerous
Total Acres
950
Parcel #
various
State Highways
I-10, SR-71, SR-66, SR-83, I-15,
Railways
UPRR, AT&SF, S.Pacific
Airports
LA/Ontario Inter.San Bernardino
Schools
numerous
Waterways
San Antonio Creek Channel, Deer Creek, Cucamonga Creek, Day Creek Channel, Etiwanda Fan
Township
1S
Range
5W
Section
20

Notice of Determination

Approving Agency
Caltrans
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print