Parker Barn Bridge Embankment Protection Project

3 Documents in Project

Summary

SCH Number
2012101061
Lead Agency
California State Polytechnic University, San Luis Obispo
Document Title
Parker Barn Bridge Embankment Protection Project
Document Type
NOD - Notice of Determination
Received
Posted
1/30/2013
Present Land Use
Outdoor Teaching and Learning, per the Cal Poly Master Plan
Document Description
Cal Poly proposes to correct current bank erosion activity in the vicinity of the Parker Barn Bridge, and to construct stable bank configurations in the eroded sections adjacent to the bridge. The project will redirect the primary streamflow pattern into a more central channel alignment away from the banks through removal of a gravel/cobble bar, and will protect the bridge abutments with riprap, willow staked benches, and brush mattress/brush layering/geotextiles. The project is subject to permitting by CDFG, ACOE, RWQCB and USFWS.

Contact Information

Name
Joel Neel
Agency Name
California State Polytechnic University, San Luis Obispo
Contact Types
Lead/Public Agency

Location

Cities
San Luis Obispo
Counties
San Luis Obispo
Cross Streets
Stenner Creek Road, Mount Bishop Road
Zip
93407
Total Acres
.15
State Highways
Hwy 1
Railways
UPRR
Schools
Cal Poly
Waterways
Stenner Creek
Township
30S
Range
12E
Base
MDB&M

Notice of Determination

Approving Agency
Trustee of the California State University
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print