Sherman Island PL 84-99 Levee Rehabilitation Project

2 Documents in Project

Summary

SCH Number
2012092029
Lead Agency
Reclamation District 341
Document Title
Sherman Island PL 84-99 Levee Rehabilitation Project
Document Type
NOD - Notice of Determination
Received
Posted
12/12/2012
Present Land Use
Agricultural

Document Description
The project work are consists of two noncontiguous segments located on the Sherman Island Levee. The project work area begins at the water side levee crest hinge point and continues landward, including the land side levee slopes of the existing levee. The 4.02-mi long eastern segment begins at Levee Station 333+00 (Lat: 38.0499; Long: 121.7039; WGS84) and ends at Levee Station 545+00 (Lat: 38.0332; Long: 121.7679). The project work area borders the San Joaquin River and Gallagher Slough. A scour pond created by a 1969 breach in the levee adjacent to the San Joaquin River occurs near the western portion of the project work area just west of the Antioch Bridge on the landward side of the levee. Sherm Island East Levee Road (a paved two-lane road) occurs on top of the levee through most of this eastern portion of the work area.

Contact Information
Emily MacDonald
Reclamation District 341
2151 River Plaza Dr., Suite #100
Sacramento, CA 95833

Phone : (916) 441-6850

Location

Coordinates
38°2'0"N 121°46'0"W
Counties
Sacramento
Cross Streets
Sherman Island Levee Road and Highway 160
Zip
94571
Total Acres
8.2
State Highways
Hwy 160
Railways
No
Airports
No
Schools
No
Waterways
San Joaquin River and Sacramento River
Township
2/3N
Range
2E
Base
MDB&M
Other Location Info
Antioch

Notice of Determination

Approving Agency
Reclamation District 341
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
Wagner & Bonsignore, CCE at 2151 River Plaza Drive, Suite #100, Sacramento, CA 95833

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print