Glenn County Solid Waste Conversion Facility (GCSWCF) Conditional Use Permit 2013-001

4 Documents in Project

Summary

SCH Number
2012082041
Lead Agency
Glenn County
Document Title
Glenn County Solid Waste Conversion Facility (GCSWCF) Conditional Use Permit 2013-001
Document Type
NOD - Notice of Determination
Received
Posted
2/22/2016
Present Land Use
Gravel Mine/M (Industrial Zone) and AE-40 (Exclusive Agricultural)/Industrial and Intensive Agriculture
Document Description
KVB, Inc. has applied for a CUP for a proposed Glenn County Solid Waste Conversion Facility. The Glenn County Solid Waste Conversion Facility includes the construction and operation of a new solid waste receiving and transfer facility, anaerobic digester (AD) facility, on-site electrical generation facility, utilities connections, compressed natural gas (CNG) production facility, and fueling station. The project will be a municipal solid waste materials recovery facility (up to 500 tons per day) and an AD facility. The MRF will consist of mechanical and manual processes are biogas, digestate, and liquid effluent. Biogas would be used onsite as a fuel for power generation, or further processed and converted to CNG.

Contact Information

Name
Andy Popper
Agency Name
Glenn County Planning & Public Works Agency
Contact Types
Lead/Public Agency

Location

Counties
Glenn
Cross Streets
South side of State Highway 32, east of County Road S, west of County Road V V
Zip
95951
Total Acres
473+\-
Parcel #
037-250-010, 037-260-004, et al.
State Highways
Hwy 32
Railways
Cal Northern
Airports
No
Schools
No
Waterways
Stony Creek
Township
22N
Range
02W
Base
MDB&M
Other Location Info
City/Nearest Community: Hamilton City

Notice of Determination

Approving Agency
Glenn County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print