Mirabel Fish Screen and Fish Ladder Replacement Project

5 Documents in Project

Summary

SCH Number
2012082040
Lead Agency
Sonoma County Water Agency
Document Title
Mirabel Fish Screen and Fish Ladder Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
7/11/2014
Present Land Use
Resource and Rural Development
Document Description
This agreement is limited to the replacement of the fish screen and modification of the fish ladder at the Mirabel facility. Project construction activities will require isolating the work area from the active flow of the Russian River, removing the existing fish screen/intake and fish ladder structures on the western bank of the Russian River, and constructing the new fish screen/intake and fish ladder structures. The new facilities will extend approximately 40 feet farther upstream and approximately 100 feet farther downstream than the existing facilities. Operation of the diversion dam and intake will not be modified by the replacement project. The California Department of Fish and Wildlife is executing a Lake and Streambed Alteration Agreement Number 1600-2013-0328-3 pursuant to Section 1602 of the Fish and Game Code to the project Applicant, Sonoma County Water Agency.

Contact Information

Name
Adam McKannay
Agency Name
CA Dept. of Fish and Wildlife Bay Delta Region
Contact Types
Lead/Public Agency

Location

Counties
Sonoma
Cross Streets
Wohler Road and Westside Road
Zip
95436
Total Acres
2
Parcel #
110-300-037
State Highways
No
Railways
No
Airports
No
Schools
El Molino HS
Waterways
Russian River, Mark West Creek, Porter Creek, Green
Township
8N
Range
9W
Section
32
Other Location Info
City/Nearest Community: Forestville

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print