Pulgas G20 Shaft Site Drainage Improvement and Erosion Repair Project

3 Documents in Project

Summary

SCH Number
2012072047
Lead Agency
San Francisco, City and County of (City and County of San Francisco)
Document Title
Pulgas G20 Shaft Site Drainage Improvement and Erosion Repair Project
Document Type
NOD - Notice of Determination
Received
Posted
10/15/2012
Present Land Use
Resource Management

Document Description
The Project includes installing a new 95 foot long box culvert south of the PG&E substation, joining the existing unnamed intermittent stream channel at or very near the current inlet and outlet, grouting and abandoning in place the existing culvert to prevent further subsidence, surface contouring the immediate surrounding area to direct storm water run-off away from the substation and installing an eight-inch diameter corrugated metal pipe (CMP) from the substation to the proposed culvert outlet. The culvert installation will also involve the construction of reinforced concrete structures at the inlet and outlet and the placement of approximately 57 CY of cement grout to abandon the existing CMP culvert.

Contact Information
Suzanne DeLeon
California Department of Fish and Game
Bay Delta Region 7329 Silverado Trail
Napa, CA 94558

Phone : (831) 440-9433

Location

Coordinates
37°28'54"N 122°19'6.94"W
Cities
San Carlos
Counties
San Mateo
Cross Streets
Canada Road
Total Acres
.5
Parcel #
093-090-070
State Highways
I-280
Waterways
Crystal Springs Reservoir
Township
4W
Section
5S

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
1650 Mission Street, Suite 400, San Francisco, CA 94103

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A Statement of Overriding Considerations was adopted for this project
N/A
(5) Findings were made pursuant to the provisions of CEQA
N/A
Download CSV New Search