Pulgas G20 Shaft Site Drainage Improvement and Erosion Repair Project

3 Documents in Project

Summary

SCH Number
2012072047
Lead Agency
City and County of San Francisco
Document Title
Pulgas G20 Shaft Site Drainage Improvement and Erosion Repair Project
Document Type
NOD - Notice of Determination
Received
Posted
10/15/2012
Present Land Use
Resource Management
Document Description
The Project includes installing a new 95 foot long box culvert south of the PG&E substation, joining the existing unnamed intermittent stream channel at or very near the current inlet and outlet, grouting and abandoning in place the existing culvert to prevent further subsidence, surface contouring the immediate surrounding area to direct storm water run-off away from the substation and installing an eight-inch diameter corrugated metal pipe (CMP) from the substation to the proposed culvert outlet. The culvert installation will also involve the construction of reinforced concrete structures at the inlet and outlet and the placement of approximately 57 CY of cement grout to abandon the existing CMP culvert.

Contact Information

Name
Suzanne DeLeon
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
San Carlos
Counties
San Mateo
Cross Streets
Canada Road
Total Acres
.5
Parcel #
093-090-070
State Highways
I-280
Waterways
Crystal Springs Reservoir
Township
4W
Section
5S

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print