Ukiah Valley Medical Center Expansion
3 Documents in Project
Summary
SCH Number
2012072001
Lead Agency
City of Ukiah
Document Title
Ukiah Valley Medical Center Expansion
Document Type
NOD - Notice of Determination
Received
Posted
9/6/2012
Present Land Use
Commercial (C) General Plan Designation: Heavy Commercial (C2) Zoning designation
Document Description
Relocation of the existing ground level heliport to the southwest corner of the roof the Emergency Department (ED) expansion at Ukiah Valley Medical Center located at 275 Hospital Drive and construction and operation of temporary heliport at the northeast corner of the Hospital Drive and Hamilton Street (APN 002-160-10). The relocated permanent rooftop heliport would be located 45 feet southeast and 20 feet higher than the existing ground level heliport. The temporary heliport will allow emergency medical flights to continue during construction of the ED expansion and the relocated permanent heliport. After the ED expansion and relocated permanent heliport have been constructed and the heliport is operation, operation of the temporary heliport would cease. No changes to the number or distribution of flights are anticipated at the temporary heliport or relocated permanent heliport.
Contact Information
Name
Kim Jordan
Agency Name
City of Ukiah
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Ukiah
Counties
Mendocino
Cross Streets
Perkins Street and Hamilton Street
Zip
95482
Total Acres
12.8
Parcel #
002-160-08, 10, 13 and 002-193-23
State Highways
Hwy 101
Railways
Northwestern Pacific
Airports
Ukiah Municipal
Schools
Various
Waterways
Gibson Creek, Orr Creek
Notice of Determination
Approving Agency
City of Ukiah
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.