Field House Expansion, Schematic Plan Approval
4 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2012071080
- Lead Agency
- California State University, San Marcos
- Document Title
- Field House Expansion, Schematic Plan Approval
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 5/22/2014
- Document Description
- The proposed project will design and construct a new gymnasium on the CSUSM campus. The new gymnasium will be approximately 26,400 SF in size and include uses such as a basketball court, locker rooms, coach's offices, bleacher seats, a box office, restrooms, storage areas, and a concession stand. The gymnasium will be able to accommodate a maximum event capacity of 1,600 spectators through the use of bleacher seating (1,400 acres) and chairs set up on the basketball court.
- Contact Information
-
Mr. Bradly Fenton
The Trustees of the CA State University
401 Golden Shore
Long Beach, CA 90802-4210
Phone : (760) 750-4659
Location
- Coordinates
- 33°7'54"N 117°9'31"W
- Cities
- San Marcos
- Counties
- San Diego
- Cross Streets
- Campus Way and Campus View Drive (on campus)
- Zip
- 92096
- Total Acres
- 1.5
- Parcel #
- 221-670-02-00 / 221-670-03-00
- State Highways
- SR 78
- Railways
- SPRINTER
- Airports
- No
- Schools
- San Marcos USD
- Waterways
- San Marcos Creek
- Township
- 12S
- Range
- 3W
- Section
- 13/14
Notice of Determination
- Approving Agency
- Trustees
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- California State University, San Marcos, Office of Facilities Planning, San Marcos CA 92096
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.