Issuance of a Revised Solid Waste Facilities Permit for the John Smith Road Landfill- Facility No. 35-AA-0001, in San Benito County

6 Documents in Project

Summary

SCH Number
2012061081
Lead Agency
San Benito County
Document Title
Issuance of a Revised Solid Waste Facilities Permit for the John Smith Road Landfill- Facility No. 35-AA-0001, in San Benito County
Document Type
NOD - Notice of Determination
Received
Posted
3/25/2013
Present Land Use
PLU: Agricultural Rangeland and Public/Quasi-Public Z/GPD: Agricultural Rangeland
Document Description
The Permit Revision will allow for an: increase in the permitted maximum tonnage received from 500 tons per day (tpd) to 1,000 tpd disposal, expand the permitted facility boundary from 57 to 90.36 acres, expand the disposal footprint from 44 to 58 acres, increase maximum elevation from 855 mean sea level (MSL) to 920 MSL, increase design capacity from 4,625,827 cubic yards to 9,354,000 cubic yards, change in estimated closure dated from 2024 to 2025 at 850 tpd or 2032 at 500 tpd, and allow designated recyclable material to not be counted towards the daily permitted tonnage per the MND analysis (permitted vehicle traffic of 600 vehicles per day will be the limiting factor on the total amount of materials received).

Contact Information

Name
Patrick Snider
Agency Name
CalRecycle
Contact Types
Lead/Public Agency

Location

Cities
Hollister
Counties
San Benito
Cross Streets
John Smith Road
Zip
95023
Total Acres
95.47
Parcel #
025-019-050, 025-019-51
State Highways
Hwy 25
Airports
Hollister Municipal
Township
13S
Range
6E
Section
4,5,8
Base
MDB&M
Other Information
Section Cont.: 9

Notice of Determination

Approving Agency
CalRecycle
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.