John Smith Road Landfill Expansion Project

6 Documents in Project

Summary

SCH Number
2012061081
Lead Agency
San Benito County
Document Title
John Smith Road Landfill Expansion Project
Document Type
NOD - Notice of Determination
Received
Posted
9/7/2012
Present Land Use
PLU: Agricultural Rangeland and Public/Quasi-Public Z/GPD: Agricultural Rangeland
Document Description
Project consists of a lot line adjustment (LLA) adding 33.81 ac to the existing John Smith Road Landfill Class lll permitted facility area, increasing the water footprint to approx. 14 acres; a 2nd LLA reducing the existing Class l area by 3.05 ac; a GPA to change the land use designation of the adjusted acreage from Agricultural Rangeland to Public/Quasi Public; a lateral & vertical landfill expansion to increase landfill capacity, with a daily permitted tonnage increase from 500 tpd to 1,000 tpd (potential input of out of county waste), with the ability to accept unlimited recyclable for diversion & re-grading of the Class l facility for temp. soil stockpiling.

Contact Information

Name
Gary Armstrong
Agency Name
San Benito County
Contact Types
Lead/Public Agency

Location

Cities
Hollister
Counties
San Benito
Cross Streets
John Smith Road
Zip
95023
Total Acres
95.47
Parcel #
025-019-050, 025-019-51
State Highways
Hwy 25
Airports
Hollister Municipal
Township
13S
Range
6E
Section
4,5,8
Base
MDB&M
Other Information
Section Cont.: 9

Notice of Determination

Approving Agency
San Benito County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.