Mid-Western Placer Regional Sewer Project

9 Documents in Project

Summary

SCH Number
2012052083
Lead Agency
City of Lincoln
Document Title
Mid-Western Placer Regional Sewer Project
Document Type
NOD - Notice of Determination
Received
Posted
9/12/2013
Present Land Use
Agriculture, Timberland, Residential, Riparian Drainage, Public Facility, & Industrial
Document Description
The Mid-western Regional Sewer Project generally consists of constructing a regional sewer system in the mid-western area of Placer County. The City of Lincoln's Wastewater Treatment and Reclamation Facility (Lincoln WWTRF) will be expanded to accommodate the existing wastewater flows from Placer County's Sewer Maintenance District No. 1 Wastewater Treatment Plant and Auburn's Wastewater Treatment Plant. The proposed project activities will occur at two wastewater treatment facilities, Lincoln WWTRF and SMD1 WWTP, and along the proposed interconnected linear alignment for the installation of regional sewer pipelines.

Contact Information

Name
Marisa Van Dyke
Agency Name
Central Valley Regional Water Quality Control Board
Contact Types
Lead/Public Agency

Location

Cities
Auburn, Lincoln
Counties
Placer
Cross Streets
Numerous
Zip
95648
Total Acres
1900
Parcel #
Multiple - Linear Project
State Highways
Hwy 49, 65, 80, & 193
Railways
UPRR
Airports
Auburn Municipal
Schools
Numerous
Waterways
Rock Creek, Dry Creek, Auburn Ravine, various
Township
12
Range
variou
Other Location Info
Newcastle

Notice of Determination

Approving Agency
RWQCB
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print