North Area Collection System Intertie (NACSI) Project
2 Documents in Project
Summary
SCH Number
2012052078
Lead Agency
City of Roseville
Document Title
North Area Collection System Intertie (NACSI) Project
Document Type
NOD - Notice of Determination
Received
Posted
7/23/2012
Present Land Use
The project area includes a mix of commercial, residential, open space, and arterial roadways/City owned right-of-way. The pipeline alignment in Segment 1 crosses lands with a General Plan designation of LI and zoned MI and GC. The Segment 2 alignment crosses lands with a General Plan designation of OS/FP and zoned OS/FW.
Document Description
The project is a proposal by the City of Roseville Environmental Utilities Department to connect existing sewer lines on the north that flow to the Pleasant Grove Wastewater Treatment Plant (PGWWTP) to existing lines on the south that flow to the Dry Creek Wastewater Treatment Plant (DCWWTP). This would be accomplished by constructing two new 10-inch sewer line segments, refurbishing and utilizing existing sewer lines, construction two new pump stations and two new pipeline under crossings of the UPRR. The two new pipeline segments would be located: 1) primarily along the west side of the UPRR within the "Telefunken" (formally NEC) campus located at 7503 Foothills Boulevard, and then west under the railroad to Industrial Avenue; and, 2) along the west side of Washington Boulevard beginning at a point approximately 300 feet south of the Washington Boulevard/Diamond Oaks Road intersection and continuing south crossing under the railroad and ending at a point approximately 380 south of the Washington Boulevard/South Branch Pleasant Grove Creek crossing.
Contact Information
Name
Mark Morse
Agency Name
City of Roseville
Contact Types
Lead/Public Agency
Phone
Location
Cities
Roseville
Counties
Placer
Cross Streets
Washington Boulevard/Diamond Oaks Road
Zip
95678
Total Acres
.8
Parcel #
017-230-048/017-113-001/017-430-ROW/017-410-ROW/017-410-032/015-350-016
State Highways
I-80
Railways
UPRR
Airports
No
Schools
Roseville Com. School
Waterways
Pleasant Grove Creek, Dry Creek
Township
11N
Range
6E
Section
34
Notice of Determination
Approving Agency
Roseville City Council
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA