Echo Water Solar Project (Lake or Streambed Alteration Agreement No. 1600-2017-0004-R2)
12 Documents in Project
Summary
SCH Number
2012052017
Lead Agency
Sacramento Regional Sanitation District
Document Title
Echo Water Solar Project (Lake or Streambed Alteration Agreement No. 1600-2017-0004-R2)
Document Type
NOD - Notice of Determination
Received
Posted
5/18/2017
Present Land Use
Public / Quasi Public
Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2017-0004-R2, pursuant to section 1602 of the Fish and Game Code to the project Applicant, Sacramento Regional county Sanitation District.
Project is limited to underground installation of 15kV rated copper conductors which would conduct electricity generated by the solar photovoltaic (PV) system from the point of generation to the Sacramento Regional Wastewater Treatment Plant (SRWTP) to the north. A directional bore method would be used to install the conductors, in order to avoid disturbance of regulated resources, including Sims Ditch, a Water of the State. Additional detail is provided in the attached supplement information document.
Directional boring will be used to avoid impacts to Sims Ditch and other sensitive resources in the project area. Locating the entry and exit points of the directional bore at least 200 feet from Sims Ditch will prevent sediment from entering the waterway. A Frac-out Plan has been prepared in case a hydraulic fracture should occur.
Contact Information
Name
Tanya Sheya
Agency Name
CDFW
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Elk Grove
Counties
Sacramento
Cross Streets
Franklin Blvd., Laguna Blvd, future Cosumnes River Blvd
Zip
95758
Total Acres
480
Parcel #
Various
State Highways
I-5
Railways
UPRR
Airports
Borges-Clarksburg
Schools
Several
Waterways
Sacramento River, Laguna Creek
Township
05E
Range
7N
Section
19
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.