Bay Area Rapid Transit (BART) Fremont Line Operability Retrofit Project
2 Documents in Project
Summary
SCH Number
2012052009
Lead Agency
San Francisco Bay Area Water Transit Authority
Document Title
Bay Area Rapid Transit (BART) Fremont Line Operability Retrofit Project
Document Type
MND - Mitigated Negative Declaration
Received
Document Description
The Fremont Line Operability Retrofit Project (proposed Project) would upgrade the Fremont Line, which is a heavily used portion of the BART system, to an "Operability" Level of retrofit. For this level of seismic upgrade, facilities would be retrofitted to a degree at which BART would be able to resume operations shortly after a major earthquake. Operability retrofits would involve construction activities that primarily consist of strengthening the existing columns and footings that support aerial structures and stations.
Ground disturbance around each pier to be retrofitted would take place within a 10-foot radius of the pier; on-site construction equipment would be placed within a 20-foot radius of each pier.
Contact Information
Name
Janie Layton
Agency Name
San Francisco Bay Area Rapid Transit District
Contact Types
Lead/Public Agency
Phone
Location
Cities
Oakland
Counties
Alameda
Cross Streets
18th Ave to Fruitvale Station; Ashland Ave; Fruitvale Station to Coliseum Station
State Highways
Hwy 77, 185, 238, 580, 880
Railways
UPRR
Airports
Oakland Int'l
Schools
6
Waterways
Alameda Creek Flood Control Channel
Other Location Info
San Lorenzo
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Fish and Wildlife, Bay Delta Region 3 (CDFW), California Department of Parks and Recreation, California Department of Transportation, District 4 (DOT), California Highway Patrol, California Native American Heritage Commission (NAHC), California Regional Water Quality Control Board, San Francisco Bay Region 2 (RWQCB), Caltrans, Division of Aeronautics, Department of Water Resources, Office of Historic Preservation, Resources Agency
Development Types
Transportation:Other (Seismic Retrofit)
Local Actions
Project approval
Project Issues
Aesthetics, Air Quality, Biological Resources, Hazards & Hazardous Materials, Noise, Transportation
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.