South Lock Repairs & Storm Water Improvements Project

3 Documents in Project

Summary

SCH Number
2012042036
Lead Agency
Bel Marin Keys Community Services District (BMKCSD)
Document Title
South Lock Repairs & Storm Water Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
6/4/2012
Present Land Use
SF6
Document Description
The BMKCSD is planning to stabilize the South Navigation Lock from settling which has been occurring since the lock was constructed in 1985. The settlement is generally a result of foundation piles which were not driven to the appropriate depth with adequate tie backs. The purpose of this project is to stabilize the South Lock, the flood control and navigational access residential homes within the South Lagoon to the Novato Creek. In addition, the project includes the construction of a sluice gate structure that connects the eastern moat (closest to the South Lock) to the Secondary Moat. The proposed improvements would include the installation of two (2) culverts, sluice gate to control floodwaters, controls and a walkway.

Contact Information

Name
Madeline Thomas
Agency Name
Bel Marin Keys Community Services District
Contact Types
Lead/Public Agency

Location

Cities
Novato
Counties
Marin
Cross Streets
Bel Marin Keys Boulevard
Zip
94949
State Highways
Hwy 101
Waterways
Novato Creek

Notice of Determination

Approving Agency
Bel Marin Keys Community Services District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print