Liberty utility 625 & 650 Line Upgrade - Timberland Conversion

6 Documents in Project

Summary

SCH Number
2012032066
Lead Agency
Tahoe Regional Planning Agency (TRPA)
Document Title
Liberty utility 625 & 650 Line Upgrade - Timberland Conversion
Document Type
NOD - Notice of Determination
Received
Posted
8/28/2015
Present Land Use
As specified in : Kings Beach, Tahoe City, Community Plan; Truckee, Placer Cournt General Plans; Mrtis Valley Community Plan
Document Description
CDFW has executed lake and streambed alteration agreement no. 1600-2015-0089-R2, pursuant to section 1602 of the fish and game code to the project applicant, Liberty Utilities. Construction of the project will require impacts to CDFW jurisdictional features at 8 sub-project locations. Impacts will include trimming, compaction, and clearing of riparian vegetation for access roads and pole installation work areas, as well as installation of 3 dry rock fords and one splitter crossing for vehicle access.

Contact Information

Name
Duane Shintaku
Agency Name
Cal Fire
Contact Types
Lead/Public Agency

Location

Cities
Nevada City, Truckee
Counties
Nevada
Cross Streets
SR 89/SR 28; SR 267/SR 28; BrockwayRoad/Donner Pass Road
Zip
96161
Total Acres
30 miles+/-
Parcel #
numerous
State Highways
SR89, SR28, SR267, I-80
Railways
Union Pacific
Airports
Truckee-Tahoe
Schools
N. Tahoe/Truckee
Waterways
Lake Tahoe, Truckee River, Griff Creek, other creeks
Other Location Info
Douglas County

Notice of Determination

Approving Agency
Cal Fire
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print