650 Transmission Line Rebuild Project (Lake or Streambed Alteration Agreement No. 1600-2015-0089-R2).
6 Documents in Project
Summary
SCH Number
2012032066
Lead Agency
Tahoe Regional Planning Agency
(TRPA)
Document Title
650 Transmission Line Rebuild Project (Lake or Streambed Alteration Agreement No. 1600-2015-0089-R2).
Document Type
NOD - Notice of Determination
Received
Posted
8/5/2015
Present Land Use
As specified in : Kings Beach, Tahoe City, Community Plan; Truckee, Placer Cournt General Plans; Mrtis Valley Community Plan
Document Description
CDFW has executed lake and streambed alteration agreement no. 1600-2015-0089-R2, pursuant to section 1602 of the fish and game code to the project applicant, Liberty Utilities.
Construction of the project will require impacts to CDFW jurisdictional features at 8 sub-project locations. Impacts will include trimming, compaction, and clearing of riparian vegetation for access roads and pole installation work areas, as well as installation of 3 dry rock fords and one splitter crossing for vehicle access.
Contact Information
Name
Patrick Moeszinger
Agency Name
CDFW North Central Region
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Nevada City, Truckee
Counties
Nevada
Cross Streets
SR 89/SR 28; SR 267/SR 28; BrockwayRoad/Donner Pass Road
Zip
96161
Total Acres
30 miles+/-
Parcel #
numerous
State Highways
SR89, SR28, SR267, I-80
Railways
Union Pacific
Airports
Truckee-Tahoe
Schools
N. Tahoe/Truckee
Waterways
Lake Tahoe, Truckee River, Griff Creek, other creeks
Other Location Info
Douglas County
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes